Valar Atomics Wins Carbon County Approval for Up to 120 Small Nuclear Reactors Near Utah Data Centers
themainewire.comCarbon County, Utah approved a permit for Valar Atomics to build a campus of 40 to 120 small modular reactors and data centers on state trust land near Wellington. The approval is not a construction permit. Each reactor still needs a license from the Nuclear Regulatory Commission, and the county added conditions including a half mile setback, three town halls, a cleanup bond, and water use limits. Valar is also pursuing a much larger plan called Project Beehive on adjacent federal land, which could host around 456 reactors and roughly 9.6 GW of capacity. The permit application includes a natural gas plant to power manufacturing, labs, and data centers before the reactors come online. Utah state senator Nate Blouin criticized that as a bait and switch. Valar's timeline calls for first reactors in 2028, but the permit expires if the company takes no substantial action within a year.