Pakistan has awarded a contract to electrify Thar coal mining operations, connecting Blocks I and II to the national grid via 132 kV transmission from Islamkot Grid Station. The project, now scheduled for completion by April 2028, will supply about 60 MW to the mines, replacing diesel generation that costs 33 cents per kWh with grid power at 13 cents. Expected savings are $25-30 million per year in foreign exchange, plus a reduction of about 80,000 tonnes of CO2 annually. The shift also supports converting diesel mining vehicles to electric, with Block I planning 40 electric trucks by end of 2026 and Block II targeting EV deployment in 2028. This move lowers the cost of coal production by roughly $0.70 per tonne, which should reduce the overall power purchase basket cost in Pakistan. Daily diesel consumption of 200,000-250,000 litres, including 35,000 litres for dewatering, will be largely replaced by cheaper electricity. The project is part of broader efforts to modernize the Thar coal field and reduce reliance on imported fuel, though the timeline and grid reliability remain key factors to watch.
