chosun.comSouth Korea wants 3.5 million electric heat pumps in homes by 2035. Government data says that would add about 8 GW of winter demand, roughly the output of six 1.4 GW nuclear reactors. The catch is timing. Heat pumps work hardest on cold nights, when solar output is near zero. The current plan leans on 163 GW of renewables by 2035, mostly solar. That does not line up with a load shape that peaks after dark. Officials say the next Basic Plan for Electricity Supply and Demand will account for the new demand, but every option has a downside. LNG or coal would weaken the carbon case, large scale storage would cost trillions of won, and new nuclear cannot be built by 2035. For anyone tracking electrification and grid policy, this is a concrete example of the gap between deployment targets and system planning. The heat pump target may still make sense, but it only works if the power plan is updated at the same time.