North Carolina regulators approved Duke Energy's latest Carbon Plan, which extends the life of some coal plants and adds roughly 3,841 megawatts of natural gas capacity between 2030 and 2033. The order also includes up to 2,300 megawatts of new solar, up to 2,700 megawatts of additional battery storage, and continued spending on advanced nuclear development. The plan is meant to keep up with rising electricity demand from data centers, manufacturing, and population growth. Notably, the decision comes after state lawmakers removed the interim 70 percent carbon reduction target for 2030, leaving the 2050 carbon neutrality goal in place. Duke will also explore pumped storage hydro and nuclear licensing at Shearon Harris and W.S. Lee. Regulators are scheduled to review the next Carbon Plan in fall 2027, when they will reassess demand forecasts and technology costs.