The final batch of turbines for the 50 MW HayWind wind farm in Mannar, Sri Lanka, has arrived at the Port of Trincomalee. Installation is already underway after the first shipment reached the country weeks ago. The project secured a power purchase agreement at USD 0.0465 per kWh, the lowest wind power tariff ever recorded in Sri Lanka. Once operational, it is expected to cut carbon emissions by roughly 186,300 metric tonnes per year and save around Rs. 4.7 billion in annual fossil fuel import costs. The wind farm supports Sri Lanka's target of 70% renewable electricity by 2030 and its net zero goal for 2050. Construction started in January 2026, with completion scheduled for March 2027. Hayleys Fentons PLC will handle turbine installation and maintenance, while the National System Operator manages grid integration.