M4 repaving project cuts emissions 50% using hydrogen, electric gear, and recycled asphalt
facilitiesmanagement-now.comA 5.7 mile section of the M4 near Swindon was repaved using hydrogen powered JCB backhoe loaders, electric planers and rollers, and recycled asphalt. The project cut CO2 emissions by 630 tonnes, a 50% improvement over conventional methods. National Highways' Low Carbon Demonstrator Fund supported the six week project. FM Conway used echelon paving to lay both lanes at once, reducing road closures. Asphalt was recycled from other motorways with mixes containing up to 60% recycled material. Manufacturing was powered by biogas from anaerobic digestion. The recycled asphalt alone saved over 400 tonnes of CO2.