Iowa Utilities Commission denies Summit Carbon Solutions bid to speed up carbon pipeline hearings
kcci.comThe Iowa Utilities Commission denied Summit Carbon Solutions' request to consolidate its phase 2 pipeline dockets and schedule hearings on an expedited timeline. The commission set hearing dates for two short segments in Floyd and Ida counties for March 23, 2027 and Feb. 23, 2027, later than the mid-December dates Summit requested. The order noted that the lawsuit over the phase 1 permit is part of the larger picture, and other phase 2 dockets remain unresolved. Summit's phase 2 expansion would add laterals to connect more biorefineries to its carbon sequestration network. The company recently announced plans to shift the route toward Wyoming and is considering enhanced oil recovery. Landowners opposing the project argue the commission should not fast-track a company that still faces legal challenges, and they are pressing candidates on property rights before the election.