Eni Liverpool Bay CCS Project Reaches 50 Percent Completion With Offshore Platform Installed
ad-hoc-news.deEni's Liverpool Bay carbon capture and storage project has reached 50 percent completion after installation of an offshore platform. The structure includes a 1,885-ton topside, a 1,755-ton jacket, and eight foundation piles weighing 730 tons combined. Eni describes it as the first purpose-built offshore platform dedicated to carbon capture and storage for industrial decarbonization. The project will take CO2 from industrial facilities in northwest England and north Wales, move it through repurposed pipelines, and store it in depleted gas reservoirs. Separately, Eni shares traded around EUR 25.00 in pre-market at Lang & Schwarz on October 12, 2026, with a bid of EUR 24.94 and an ask of EUR 25.06. For readers tracking CCS deployment, the milestone shows the project moving from design into physical construction. The missing detail is the final injection timeline and whether nearby industrial emitters have signed binding contracts for the captured volumes.