Eni, through its CCUS Holding joint venture with Global Infrastructure Partners, has completed installation of the Douglas CCS platform in Liverpool Bay. The platform will act as the offshore hub for the HyNet cluster, collecting CO2 from industrial sites in northwest England and North Wales and sending it through repurposed pipelines to depleted gas reservoirs under the seabed. The company says it is the first purpose-built offshore platform dedicated to CCS for industrial decarbonization. The project combines 1,885 tonnes of topsides, a 1,755-tonne jacket, and 730 tonnes of foundation piles. Eni says the wider Liverpool Bay CCS network is about 50% complete, with 149 km of existing pipelines being repurposed and 35 km of new pipelines being built. First-phase storage capacity is 4.5 million tonnes of CO2 per year, with potential to reach 10 million tonnes in the 2030s. Construction is expected to start this year, with planned startup in 2028.