DOE awards TerraSpark $18.5M for West Virginia coal plant carbon capture project near Mount Storm
wvnews.comThe U.S. Department of Energy has awarded up to $18.5 million to TerraSpark Energy for its proposed 1.6-gigawatt coal-fired power plant with carbon capture technology near Mount Storm, West Virginia. The funding supports early development of the TerraSpark Energy Campus, a project that aims to combine coal generation with carbon capture to reduce emissions while maintaining baseload power. The award comes from DOE's carbon capture demonstration program and will cover design, permitting, and front-end engineering. TerraSpark says the plant could capture up to 90% of its CO2 emissions, though the technology has not yet been proven at this scale on a coal plant. The project faces significant questions about cost, timeline, and whether the captured carbon will have a viable storage or utilization pathway.