Cypress Creek Breaks Ground on 5.4 GW Solar-Storage Hub in Arkansas to Power Google Data Centers and Regional Grid
energytech.comCypress Creek Energy has started construction on the Steel River Energy Center in Mississippi County, Arkansas, a 5.4 GW solar and battery storage project. The first two phases add 1.63 GW of solar and 1.9 GW of storage, with full completion expected by 2029. Google has signed a power purchase agreement for the first two phases to supply carbon-free electricity for its data centers in West Memphis and Little Rock. The project uses 100% U.S.-made solar panels from First Solar, structural steel from U.S. Steel's Big River facility, and lithium-ion batteries from LG Energy Solution Vertech assembled in U.S. factories. An initial $3.5 billion investment was arranged by Barclays, BNP Paribas, Santander, and Wells Fargo. Cypress Creek estimates the project will generate $300 million in local tax revenue over its lifetime and support 700 construction jobs.