Channel Islands extend low-carbon power imports from France until 2032
bailiwickexpress.comGuernsey and Jersey electricity firms have signed a new contract with EDF to continue importing low-carbon electricity from France until at least 2032. The deal starts in January 2028 and runs for four years, building on the existing arrangement. The imported power flows through subsea cables and covers over 90% of Guernsey's annual demand, reducing reliance on the island's fossil fuel power station. However, the existing cable cannot meet peak winter demand, so diesel generators still run during cold months. A proposed second direct cable to France was not pursued, so the islands remain dependent on the current link and on French grid decarbonization. The contract includes forward price hedging to smooth tariff volatility, but questions remain about whether the grid can keep up with future demand growth.